Anticipated Delivery Schedule

Summer 2005 Groundbreaking

Spring 2006 Excavation Complete

Fall 2006 Structure at Grade

Spring 2007 Structure Complete (topping out)

Fall 2007 Exterior Facade Complete (close in)

Spring/Summer 2008 First Unit Deliveries/Building Completion

Current Activities  

Bovis was working steadily throughout the summer and construction is rapidly progressing.The building has permanent power and the curtain wall (windows and zinc panels) continues to be installed. Drywall work should commence in the units over the next month.Meanwhile the kitchen cabinets and closet systems now are arriving at the port in Baltimore.Currently, building occupancy is expected to start in the spring of 2008 and extend into the summer months.


22 West
Sales Office

Sales by:
EastBanc Marketing, LLC
1177 22nd Street, N.W.
Suite 1C
Washington D.C. 20037

T 202.333.3313
F 202.333.2013


email

Directions to
Sales Office